Glenoaks Blvd. Rehabilitation Meeting Notes

Last Monday night, at the Glenoaks Elementary auditorium, a meeting was held to discuss the rehabilitation project to resurface Glenoaks Blvd. and many of the surrounding streets in our canyon. Below are the notes from that meeting.

Councilman Dave Weaver first spoke. He mentioned that on March 27th the city will have a study session on the Glendale Master Bike Plan. He urged all of us to attend this council meeting to voice our opinions and hear what is being discussed regarding bike paths in the canyon and throughout Glendale. Currently, the meeting is scheduled for   3pm but he's trying to get it changed to 6pm. If we get a better idea of when the meeting will be held, we will post the time on the website. The City Council will also be discussing the rehab project at their meeting on Tuesday 3/13. Bike lanes are being proposed but as of now are not part of the plan but the Council will be getting bids just in case.

The City Works Dept. gave a presentation outlining what types of resurfacing and repair will be done on what sections of the canyon. You can view the presentation here (please note this is a relatively large file).

The project is anticipated to being around June 4th and will take approximately 3 months to complete. All work in front of the school will be done during the summer break.

For much of the work where a slurry seal or complete resurfacing will take place, you will not be able to get access to your property from 7am to 5pm the day that they are laying the asphalt. That means if you do not leave your house on that day you will have to stay home until 5pm that evening, or if you leave (before 7am) you will not be allowed to return until after 5pm. This includes walking as well as driving. Of course if there is a life threatening emergency, all bets are off. This will be done in sections and several notices will go out to the residences affected for each section giving plenty of notice before the street is closed.

When they are doing Glenoaks Blvd. they will be doing half of the roadway at a time so there will always be a means to get in and out of the canyon.

Once the paving phase is complete, the roads will be striped and painted. The center divider that is no on Glenoaks Blvd. Will be removed and there will be a center line only. There is a proposal to continue a bike lane from Verdugo Blvd. Along Glenoaks Blvd up to Scholl Rd. (where the road is wider) and then have sharrow markers the rest of the way up the canyon. This is a proposal only and has not yet been voted on.

Three trees will have to be removed for this project. Two of them are already dead. Once complete, the city will be planting 55 new trees along the roadways within the canyon.